First check what has been handed over
The technical specification (technische omschrijving) states how your home is handed over. Walls are often wallpaper-ready (behangklaar), ceilings usually have a white sprayed finish, and the floor is a screed, often with underfloor heating.
Wallpaper-ready is not the same as paint-ready (sausklaar). If you want the walls painted, they first have to be made suitable for that. This is the first choice that shapes the rest of the schedule.
The order, step by step
Work from rough to fine and from top to bottom. Whatever creates dust, water or splashes comes first; whatever is delicate comes last.
Painting before the floor avoids paint splashes on a new floor. Skirting boards come after the floor, because they cover its edge. Sometimes a short round follows to touch up skirting and joints.
- extra walls, ceilings and plastering
- priming and painting walls and ceilings
- laying the floor, with underlay
- skirting boards, trims and adjusting doors
- sealant work and the last touch-ups
Construction moisture and underfloor heating
A new home holds a lot of construction moisture, in concrete, screed and plaster. It has to leave before a floor can lie well. Ventilating and heating gently help; heating hard too quickly can cause cracks.
Underfloor heating comes with a heating-up protocol: the temperature goes up and down again in steps before the floor is laid. The builder or installer and the floor manufacturer state how to do this. Allow time for it; it often decides the earliest date for the floor.
Kitchen, bathroom and installations
Kitchen, bathroom, tiling and electrics are done by other companies. Agree with them who is in the house when, so that nobody has to work over a newly laid floor.
Whether the kitchen comes before or after the floor differs per kitchen and floor. Ask the kitchen supplier what they need and pass that on to us.
What can one crew do in one schedule?
Noordvaro takes on the finishing work after handover: painting walls and ceilings, laying laminate or click PVC, fitting skirting boards, adjusting doors and, where wanted, building an extra wall. Those parts then follow one another in a single schedule.
We do not carry out smooth plastering, kitchens, bathrooms, tiling or electrics. You plan those with the companies concerned; we fit our order around them.